21
Design, manufacturing, commissioning, and start-up of a galvanic technological complex consisting of V-TPV2-1600/1600/12-P-UHL4
3
2014
22
Design, manufacture, adjustment, and commissioning of the technological complex for electroplating consisting of: automated workstation (AWP)
1
2014
23
Development of design documentation, working drawings, software, manufacturing and supply of control cabinet and automatic control cabinet (SAC), modernization, commissioning, and start-up of DC drive PTP-3200 “Tandem 650” CHPP-1
1 set.
2014
24
Development, manufacturing, and testing of a power supply unit for testing electrical equipment of metro cars IPT-500-1000-UHL4
1
2013
25
Design, manufacturing, installation, commissioning, and start-up of the excitation system STRP-2000-350-2.0-UHL4 for TG-No.1 (60 MW)
1
2012
26
Supply of a dynamic braking control cabinet
1
2012
27
Design and manufacturing of equipment for major overhaul of the DC drive of pressing screws 2800 stand; 1000 А, 440 V
1 set
2012
28
Design, manufacturing, installation, commissioning, and start-up of a 2-channel ARV (SHARV-300-1) for TG-No.11 (TGV-300)
1
2012
29
Design and manufacture V-TPE8-315-48-I-UHL4
1
2012
30
Design, manufacture, and testing of the power supply for the electroplating bath V-TPE2-200/12-I-UHL4 (non-reversible, inverter, 200 А, 12 V)
6